Main Navigation

U summer 2018 traffic updates

Find the latest updates on the UDOT summer construction projects.

[Tuesday, Aug. 14, 2018] NORTH CAMPUS DRIVE DAYTIME LANE RESTRICTIONS TOMORROW

  • NORTH CAMPUS DRIVE DAYTIME LANE RESTRICTIONS: Tentative North Campus Drive daytime lane restrictions in effect for Wednesday, Aug. 15. Crews will be working on the median islands near Wasatch Drive. A lane in each direction will be intermittently closed throughout the day.

[Thursday, July 26, 2018] NORTH CAMPUS DR. LANE CLOSURES IN PLACE

  • NORTH CAMPUS DRIVE: Unplanned North Campus Dr. lane closures for tonight and tomorrow.
    • Both EB lanes and one WB lane currently open.
    • Starting at 7 p.m. tonight, through tomorrow afternoon, only one lane in each direction will be open.
    • Motorists are encouraged to use alternative routes.

[Wednesday, July 25, 2018] ROAD CLOSURES AND UPDATES

  • North Campus Drive: Pavement removal and replacement continues this week. One lane in each direction is open in the evenings. All lanes are open during the daytime hours.

    Please note: the speed limit along North Campus Drive is reduced to 15 miles per hour in both directions during construction.

    Flaggers on Site: Flaggers will be at adjacent side streets to assist motorists who need access as equipment comes through.

    Alternate Routes Encouraged: Bicycles and motorcycles are strongly encouraged to use alternate routes due to loose gravel on North Campus Drive during construction.

    Impacts: Expect noise, dust, and vibration.

    Drive safely in the work zone:

  • Obey the speed limit, 15 MPH at all times, in both directions
  • Be aware of the uneven lanes
  • Alternate routes are encouraged

  • South Campus Drive: Sign installation will begin on Sunday night. Roads closures will be in place but access will be available. Look for flaggers directing traffic onto South Campus from Mario Capecchi Drive for westbound access. For eastbound access please enter South Campus at Campus Center Drive.

  • Mario Capecchi Drive: Crews are installing signs and raising utilities this week. During the evening hours one lane in each direction will be open.

[Monday, July 16, 2018] July 16-22 ROAD CLOSURES AND UPDATES

  • NORTH CAMPUS DRIVE:
    • Tuesday night: Crews will remove asphalt in the westbound lanes until 10 p.m. One lane in each direction will be open and traffic will be shifted into the eastbound lanes. At 10 p.m., crews will close the south half (eastbound lanes) of the intersection at Mario Capecchi and North Campus Drive to remove and replace asphalt. This work will be complete and the intersection will be reopened by 6 a.m.
    • Wednesday night: Crews will close the north half of the intersection at Mario Capecchi and North Campus Drive to complete asphalt removal and replacement. This work will be complete and the intersection will be reopened by 6 a.m.

    • Rest of the week: Crews will continue removing and replacing asphalt on North Campus through Saturday night. One lane in each direction will be open. Pay attention to signage.

    • Flaggers on site: Flaggers will be at adjacent side streets to assist motorists who need access as equipment comes through.

    • Alternate routes encouraged: Bicycles and motorcycles are strongly encouraged to use alternate routes due to loose gravel on North Campus Drive during construction.

    • Impacts: Expect noise, dust, and vibration.

      Updates from UDOT are also available by calling 1-888-556-0232 or emailing campusdrive@utah.govClick here for more information.


  • SOUTH CAMPUS DRIVE: Asphalt removal and replacement is complete. Pavement markings will be installed tonight. Drive safely through the work zone. Updates from UDOT are also available by calling 1-888-556-0232 or emailing campusdrive@utah.gov.

  • MARIO CAPECCHI: No work is taking place this week. Evening utility work is expected as soon as July 25.  Currently, all lanes are open. Updates from UDOT are also available by calling 1-888-556-0232 or emailing campusdrive@utah.govClick here for more information.

[Tuesday, July 3, 2018] July 2-8 updates

South Campus Dr.: Asphalt removal and replacement will be completed this week. Crews will be grinding the road surface to install striping and pavement markings later this week. Expect single lane closures and the work to move quickly.
At least one lane in each direction will be open between 6 am to 7 pm.
North Campus Dr.: Crews have begun saw cutting the concrete islands between Central Campus and Federal Heights Drive and will remove them later this week. This work will result in an edge drop-off for the inside traffic lanes. The islands will be reconstructed after the roadway construction is complete. Expect very loud noise during the island removal operation.
Please note: speed along North Campus Dr. will be reduced to 15 miles per hour in both directions during construction.
 
Drive safely in the work zone:
  • Obey the speed limit, 15 miles per hour at all times, in both directions
  • Be aware of the edge drop-off on the inside lane in both directions
  • Alternate routes are encouraged
During the day, both lanes eastbound will be open and one westbound lane will open. However, the speed is reduced to 15 miles per hour at all times in both directions.  Noise, dust, vibration and lights are also impacts. This work will occur the evenings of July 1, 2, 5 and 6. No construction will take place the nights of July 3 and 4. 
Remaining North Campus Dr. construction comprising asphalt removal and replacement is anticipated to begin as early as mid-July.
Work for North Campus Dr. has shifted to nights and weekends.
Mario Capecchi Dr.: No work is taking place this week. All lanes are open.

The UDOT project team remains committed to completing reconstruction prior to the beginning of Fall semester.

*Construction is a dynamic activity and the schedule is subject to change. 

[Friday, June 29, 2018] NORTH CAMPUS DR. CONSTRUCTION BEGINS THIS WEEKEND

Crews will begin removing the islands between Central Campus Dr. and Federal Heights Dr. the evening of Sunday, July 1. This work will result in an edge drop-off for the inside traffic lanes. Expect very loud noise during the island removal operation.
 
Drive Safely in the Work Zone:

  • Obey the speed limit, 15 MPH at all times, in both directions
  • Be aware of the edge drop-off on the inside lane in both directions
  • Alternate routes are encouraged

During the day, both lanes eastbound will be open and one westbound lane will open. However, the speed is reduced to 15 miles per hour at all times in both directions.  Noise, dust, vibration and lights are also impacts. This work will occur the evenings of July 1, 2, 5, and 6. No construction will take place the nights of July 3 and 4.

Remaining North Campus Dr. construction comprising asphalt removal and replacement is anticipated to begin as early as mid-July.

Work for North Campus Dr. has shifted to nights and weekends.


[Tuesday, June 26, 2018] MARIO CAPECCHI OPEN THROUGH MID-JULY, SOUTH CAMPUS CONSTRUCTION CONTINUES

MARIO CAPECCHI: Paving and striping are complete and Mario Capecchi is fully open through mid-July, before crews come back to complete utility work. Updates on construction will be available as this works gets closer.

SOUTH CAMPUS DRIVE: Crews will begin removing and replacing asphalt tonight, going west bound from Mario Capecchi. Work will take place on nights and weekends.
Pavement maintenance on South Campus Drive will move quickly. Be aware of lane shifts. Expect noise, dust, vibration and heavy equipment near the roadway.
At least one lane in each direction will be open between 6 am to 7 pm. Expect single direction closures between 7 pm to 5 am.

[Monday, June 25, 2018] ASPHALT REMOVAL, LANE SHIFTS

UDOT to remove and replace asphalt tonight, west bound from Mario Capecchi. Work will take place on nights/weekends and will move quickly. Be aware of lane shifts. Expect noise, dust, vibration and heavy equipment near the roadway. Lanes will be open for the morning and evening commutes.


[10 a.m. Tuesday, June 19, 2018] Updates for June 18-24

Mario Capecchi Drive: UDOT crews will be grinding the road surface to install striping and pavement markings this week. Expect single lane closures and the work to move quickly. Signs will be replaced this weekend and into early next week.

All lanes will be open during peak commute times. Northbound closure time is 7 p.m. to 6 a.m. Southbound closure time is 8 p.m. to 8 a.m.

South Campus Drive: ADA ramp reconstruction and pedestrian button adjustment continues. Asphalt removal and replacement is anticipated to begin as early as the night of June 25.

Pavement maintenance on South Campus Drive will move quickly. Please pay attention to signage and be aware of lane shifts if you drive on South Campus during construction. Work will take place during night and weekend hours.

North Campus Drive: Construction is anticipated to begin as early as the week of July 1. Work for this phase of the project has shifted to nights and weekends.

Once construction begins, expect significant speed reductions of as low as 15 miles per hour. The road surface will be uneven, motorists need to leave extra space between other vehicles to compensate for road conditions and delays are probable. Plan extra commute time or use Foothill Drive.

The project team remains committed to completing reconstruction prior to the beginning of fall semester.

*Construction is a dynamic activity and the schedule is subject to change. 


[2:30 p.m. Friday, May 25, 2018] No holiday construction work

UDOT will not be performing any road construction work this holiday weekend from 3 p.m. on Friday, May 25, through 5 a.m. Tuesday, May 29.
Surfaces between lanes on Mario Capecchi may be uneven as asphalt removal takes place. Merge lanes early to improve safety and please pay attention to signage if in the area.

[8 a.m. Thursday, May 18, 2018] North Campus Dr morning commute

North Campus Drive: North Campus Drive morning traffic may be impacted by construction equipment. Crews working this morning to get the equipment moved.

[3:30 p.m. Friday, May 18, 2018] Weekend lane closures on Mario Capecchi

Mario Capecchi Drive: The outside southbound lane and shoulder will be closed as crews update pedestrian ramps between North Campus Drive and Foothill Drive this weekend. At minimum, one lane in each direction on Capecchi will remain open. 

All crossings remain fully accessible. In some locations temporary ramps may be added to allow newly-poured concrete to cure around the existing ramps. Please pay attention to and follow signage if you will be in the area. 


[5 p.m. Wednesday, May 16, 2018] Nightly lane closures, rotomilling on Mario Capecchi

The work on Mario Capecchi Drive has begun. Single lane closures are scheduled to occur nightly. It is recommended that motorists leave early and plan for extra time — 15-minute delays can be expected.
 
Tonight, Wednesday, May 16, crews will be working on: lowering utilities, installing new traffic detection devises for signals and ADA improvements to sidewalks.
 
Nighttime rotomilling on Mario Capecchi will begin Thursday, May 17.
 
Roads will be continue to be open during the morning and afternoon commutes.

During this project, all lanes on Mario Capecchi Drive are scheduled to remain open during daytime hours and during the morning and afternoon commutes. One lane will remain open in each direction during night work, and 24/7 on the weekends.​


[11 a.m. Tuesday, May 15, 2018] Pedestrian ramp removal and replacement beginning on Mario Capecchi Dr tomorrow

Overnight, UDOT filled in the portion of North Campus Drive that had previously been chipped out. The road is back to full capacity for the time being with 2 lanes eastbound (toward the main medical campus) and 2 lanes westbound (away from the main medical campus). Construction on this road is postponed while UDOT collaborates with the university to revise the construction and traffic plan. 
 
UDOT crews will begin removing and replacing pedestrian ramps along Mario Capecchi Dr on the northbound side at night beginning Wednesday, May 16. 
  • Anticipate some additional nighttime noise from concrete removal, additional trucks and construction equipment.
  • Locations are being confirmed. If you need access assistance, please contact the project team.
Asphalt removal and replacement is planned to begin the night of May 20.
 
No work is planned for the nights of Saturday, May 26 through Monday, May 28, in recognition of the Memorial Day holiday.
 
*construction schedules are subject to change 

[4:45 p.m. Monday, May 14, 2018] North Campus Dr lane closures for tonight through 6 a.m. Tuesday, May 15

North Campus Dr LANE CLOSURES: UDOT crews will reduce North Campus Drive to one eastbound lane from 7 p.m. tonight, Monday, May 14 to 6 a.m. Tuesday, May 15, while temporary asphalt is placed. Salt Lake City Police Department will be present to assist traffic.

Following this work, all lanes will remain open until the traffic management plan is adjusted. 


[12 p.m. Monday, May 14, 2018] Mario Capecchi construction to begin, North Campus Dr work postponed

In response to major delays on North Campus Drive last week, the Utah Department of Transportation (UDOT) is postponing work on the road while UDOT collaborates with the university to revise the construction and traffic plan. In the meantime, UDOT is shifting its resources to begin asphalt removal and replacement on Mario Capecchi Drive between North Campus Drive and Foothill Drive.

The work on Mario Capecchi Drive is planned to begin tomorrow, Tuesday, May 15. Single lane closures are scheduled to occur nightly. It is recommended that motorists leave early and plan for extra time — 15-minute delays can be expected.

All lanes will remain open to accommodate traffic during the morning and afternoon commutes. One lane will remain open in each direction during night work, and 24/7 on the weekends.

North Campus Drive Project background:

UDOT has been working closely with the University of Utah in planning for work to be done on North Campus Drive. Following the plan’s implementation last week, it was determined that changes were necessary to ensure each organization’s commitment to:

  • Maintaining access to all hospitals and clinics for emergency crews, patients, and staff.
  • Providing a safe work zone width for construction crews.
  • Reducing the timeframe of the project to ensure the lowest possible traffic impact.

More information about plans for North Campus Drive will be provided as confirmed.

Updates from UDOT are available by calling 1-888-556-0232 or emailing campusdrive@utah.gov. Those updates will also be posted on Twitter @uofutraffic and online on @theU. Twitter users can receive text message updates on the project by texting "Follow @uofutraffic" to 40404.


[12:30 p.m. Friday, May 11, 2018] North Campus Dr currently open

The two eastbound lanes on North Campus Drive (toward the hospital) are currently open. One westbound lane (away from the hospital) is also open and operational. Further restrictions in this area can be expected as UDOT and the university work to find a solution to the traffic congestion issues experienced earlier this week. We will continue to provide updates as information becomes available.

Updates from UDOT are also available by calling 1-888-556-0232 or emailing campusdrive@utah.gov. Those updates will also be posted on Twitter @uofutraffic and online on @theU. Twitter users can receive text message updates on the project by texting "Follow @uofutraffic" to 40404.


[7 p.m. Thursday, May 10, 2018] North Campus Dr lane restriction update

The two eastbound lanes on North Campus Drive (toward the hospital) are open and fully operational at this time. One westbound lane (away from the hospital) is also open and operational. Further restrictions in this area can be expected as UDOT and the university work to find a solution to the traffic congestion issues experienced earlier this week. We will continue to provide updates as information becomes available.​


 

[4:30 p.m. Wednesday, May 9, 2018] Where to find updates

Updates from UDOT are also available by calling 1-888-556-0232 or emailing campusdrive@utah.gov. Those updates will also be posted on Twitter @uofutraffic. Twitter users can receive text message updates on the project by texting “Follow @uofutraffic” to 40404.

Additionally, UDOT and the university have:

  • Enhanced directional signage along Central Campus Drive and Wasatch Drive
  • Extended green signals on Mario Capecchi to move traffic through faster
  • Added officers and flaggers during peak times around Mario Capecchi and North Campus to augment traffic lights
  • Opened East Medical Drive for southbound traffic after 2:30 p.m. The road is currently closed for utility work for the rehabilitation hospital
  • Changed two northbound lanes on Mario Capecchi Drive to right turn lanes to facilitate traffic to the hospital
  • Adjusted westbound lanes from North Medical to left turn lanes on Mario Capecchi Drive

Commuters and visitors should expect delays for the duration of this project, which is expected at the end of June. Drivers are encouraged to slow down, follow the signage posted, and be safe. Your patience throughout this project and other summer construction is appreciated.